Project Management

Project Management
We Also Provide SYNOPSIS AND PROJECT.
Contact www.kimsharma.co.in for best and lowest cost solution or
Email: amitymbaassignment@gmail.com
Call: 0 +91 82907-72200 (Call/WhatsApp) or +91 88003-52777 (WhatsApp Only)

QUESTION 1
The three phases involved in the management of large projects are

“Scheduling, operating, evaluating”

“Planning, scheduling, evaluating”

“Scheduling, designing, operating”

“Planning, scheduling, controlling”

QUESTION 2
A dummy activity is required when

The network contains two or more activities that have identical starting and ending events

Two or more activities have different ending events

Two or more activities have the same ending events

Two or more activities have the same starting events

QUESTION 3
“With respect to PERT and CPM, slack”

Is a task or subproject that must be completed

Marks the start or completion of a task

Is the amount of time a task may be delayed without changing the overall project completion time

Is the latest time an activity can be started without delaying the entire project

QUESTION 4
Which of the following is a basic assumption of PERT?

There is only one complete route from the start of a project to the end of a project

No activity in the network must be repeated.

Activity completion times are known with certainty

Only critical path activities in the network must be performed

QUESTION 5
Which of the following is a direct responsibility of the project manager?

Calculating completion probabilities for all tasks in the project

Drawing the network diagram

“Making sure that the people assigned to the project receive the motivation, direction, and information needed to do their jobs”

Performing all of the activities in the project

QUESTION 6
“When checking the calendar of a team member to schedule a meeting, you see she has scheduled a meeting with a key stakeholder that you were not informed of. The best approach would be to”

Avoid mentioning it to the team member but continue to watch her activities

Notify your boss about the problem

Address the concern with the team member’s boss

Address the concern with the team member

QUESTION 7
Project A has an internal rate of return (IRR) of 21 percent. Project B has an IRR of 7 percent. Project C has an IRR of 31 percent. Project D has an IRR of ig percent. Which of these would be the BEST project?

Project A

Project B

Project C

Project D

QUESTION 8
PERT analysis computes the variance of the total project completion time as

The sum of the variances of all activities on the critical path

The sum of the variances of all activities in the project

The variance of the final activity of the project

The sum of the variances of all activities not on the critical path

QUESTION 9
Which of the following is not a potential for a ranking problem between two mutually exclusive projects?

The projects have unequal lives that differ by several years

The costs of the two projects differ by nearly 30%.

The two projects have cash flow patterns that differ dramatically

One of the mutually exclusive projects involves replacement while the other involves expansion

QUESTION 10
A project whose acceptance does not prevent or require the acceptance of one or more alternative projects is referred to as __________

a mutually exclusive project

an independent project

a dependent project

a contingent project

QUESTION 11
“If all planned work has been completed or earned,What is the schedule variance?”

0.01

0

0.1

0.5

QUESTION 12
Which of the following statements is correct regarding the internal rate of return (IRR) method?

Each project has a unique internal rate of return

“As long as you are not dealing with mutually exclusive projects, capital rationing, or unusual projects having multiple sign changes in the cash-flow stream, the internal rate of return method can be used with reasonable confidence”

The internal rate of return does not consider the time value of money

The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated

QUESTION 13
“In, ____________we see whether return or benefits on this investment are more than its cost from point of view of society in which we are living”

Social cost benefit analysis

Cost benefit analysis

Profit analysis

Risk analysis

QUESTION 14
“When operating under a single-period capital-rationing constraint, you may first want to try selecting projects by descending order of their __________ in order to give yourself the best chance to select the mix of projects that adds most to firm value.”

profitability index (PI

net present value (NPV)

Internal rate of return (IRR)

payback period (PBP)

QUESTION 15
Resource leveling will generally

Reduce the time needed to do the project

Increase the total time necessary to do all the tasks

Reduce the overutilization of resources

Reduce resources to the lowest skill that is possible

QUESTION 16
A project manager is using a cause and effect diagram with the team to determine how various factors might be linked to potential problems. In what part of the quality management process is the project manager involved?

Quality analysis

Perform quality assurance

Perform quality control

Quality planning

QUESTION 17
The act of doing anything that will help to bring future project performance into line with the project plan is called

Budget update

Revised cost estimate

Corrective action

Contingency planning

QUESTION 18
A project manager would like to manage his project in such a way that he will be able to identify specific tasks that should be watched and managed more closely than others. The project manager should use which method?

The PERT method

The critical path method

The GERT method

The PCDM method

QUESTION 19
Which of the following managers develop operational plans for the project?

Top Managers

Middle Manager

Line Managers

Supervisors

QUESTION 20
The program evaluation and review technique (PERT) method of scheduling differs from the critical path method (CPM) because the PERT method:

Uses weighted averages of activity durations to calculate project duration

Uses ..dummy.. activities to represent logic ties

Uses ..free float.. instead of ..total float.. in the schedule calculations

Uses bar charts instead of logic diagrams to portray the schedule

We Also Provide SYNOPSIS AND PROJECT.
Contact www.kimsharma.co.in for best and lowest cost solution or
Email: amitymbaassignment@gmail.com
Call: 0 +91 82907-72200 (Call/WhatsApp) or +91 88003-52777 (WhatsApp Only)

Leave a Reply

Your email address will not be published. Required fields are marked *